Which of the following is an update from control schedule in project management plan?

  1. Schedule data, project schedule, risk register

  2. Schedule baseline, schedule management plan, cost baseline

  3. Project charter, project management plan

  4. Existing formal and informal cost estimating and budgeting policies

The correct answer is: Schedule baseline, schedule management plan, cost baseline

The correct answer is B. In project management, an update from control schedule in the project management plan would typically include the schedule baseline, schedule management plan, and cost baseline. These elements are crucial for monitoring and controlling the project schedule and costs to ensure that the project stays on track and within budget. Option A is incorrect because while schedule data and the project schedule may be updated during the control schedule process, the risk register is typically updated as part of the risk management processes, not control schedule. Option C is incorrect because the project charter and project management plan are not typically updated during the control schedule process. They are more likely to be updated during the planning phases or when significant changes occur in the project. Option D is incorrect because existing formal and informal cost estimating and budgeting policies are related to cost management, not schedule control.