What is an output of the estimate activity resources process?

  1. Resource leveling plan

  2. Resource breakdown structure

  3. Stakeholder register

  4. Scope baseline

The correct answer is: Resource breakdown structure

The output of the estimate activity resources process is the Resource breakdown structure (RBS). The RBS is a hierarchical structure that identifies and organizes the resources required for the project. It provides a breakdown of resources by category and type, contributing to better management and allocation of resources throughout the project lifecycle. Regarding the other options: A. Resource leveling plan is an output of the Develop Schedule process. C. Stakeholder register is an output of the Identify Stakeholders process. D. Scope baseline is an output of the Define Scope process.