What is an output of the determine budget process?

  1. Quality metrics

  2. Cost baseline

  3. Stakeholder register

  4. Communications management plan

The correct answer is: Cost baseline

The correct answer is B. Cost baseline. During the Determine Budget process in project management, the cost baseline is an important output. The cost baseline is the approved version of the project budget, which includes all authorized project funding, and represents the time-phased project budget for the project work. It is used as a basis for measuring and monitoring project cost performance. While quality metrics, the stakeholder register, and the communications management plan are all important components in project management, they are not direct outputs of the Determine Budget process.