What does the planning process in project management aim to achieve?

  1. To monitor and control the project's progress

  2. To define objectives and plan the actions required to attain them

  3. To allocate the project budget across tasks

  4. To document lessons learned and close the project

The correct answer is: To define objectives and plan the actions required to attain them

The planning process in project management aims to define objectives and plan the actions required to attain them. This stage involves determining the project's scope, setting goals, establishing timelines, identifying resources needed, and outlining the tasks to be completed. By defining objectives and planning necessary actions, the project team can align their efforts towards achieving a common goal and successfully completing the project. This process sets the foundation for the project's execution and control phases. Options A, C, and D are not correct because they do not accurately describe the primary purpose of the planning process in project management. Monitoring and controlling the project's progress, allocating the project budget, and documenting lessons learned are tasks that occur during different phases of the project lifecycle and are not the primary objectives of the planning process.