What are the outputs of the collect requirements process?

  1. Requirements documentation and traceability matrix

  2. Project charter and scope management plan

  3. Project scope and description

  4. Comparable organization best practices

The correct answer is: Requirements documentation and traceability matrix

The collect requirements process is a part of the project management process which involves gathering and documenting the project requirements from stakeholders. Since the main objective of this process is to collect requirements, option A, which mentions requirements documentation and traceability matrix, is the correct answer. Options B and C are incorrect as they refer to other project management processes and deliverables, such as the project charter and scope management plan, and project scope and description. Option D is also incorrect as it does not mention any outputs related to gathering requirements.