What are the inputs of close procurements?

  1. Work performance data

  2. Procurement documents and project management plan

  3. Change logs

  4. Vendor agreements

The correct answer is: Procurement documents and project management plan

The inputs of close procurements include procurement documents and the project management plan. During the close procurements process, it is essential to review and gather all relevant procurement documents to ensure that each contract has been fulfilled and closed properly. Additionally, the project management plan is a key input as it provides guidance on how to properly close out procurement contracts within the project's scope and objectives. Therefore, option B is the correct answer. Work performance data, change logs, and vendor agreements are not specific inputs of the close procurements process. Work performance data is more relevant to monitoring and controlling project work, change logs are linked to the perform integrated change control process, and vendor agreements are related to procurement management throughout the project life cycle.