What are outputs of perform qualitative risk analysis?

  1. Risk appetite and risk categories

  2. Project documents updates

  3. Risk triggers and risk owners

  4. Risk management plan

The correct answer is: Project documents updates

The outputs of performing qualitative risk analysis include project document updates. The other options are incorrect because risk appetite and risk categories are inputs to the process, risk triggers and risk owners are outputs of performing quantitative risk analysis, and the risk management plan is a tool and output of the process, not an output itself. Therefore, project document updates are the only output of performing qualitative risk analysis.