CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM exam with our comprehensive quiz that includes engaging questions, detailed explanations, and ample practice resources to help you succeed.

Practice this question and more.


What are inputs of the collect requirements process?

  1. Scope baseline and project schedule

  2. Feedback from stakeholders and performance data

  3. Expert judgment and decision making

  4. Scope management plan, requirements management plan, stakeholder management plan, project charter, stakeholder register

The correct answer is: Scope management plan, requirements management plan, stakeholder management plan, project charter, stakeholder register

The inputs of the collect requirements process are crucial documents and plans that help in gathering the project requirements efficiently. The correct answer, option D, includes essential inputs such as the scope management plan, requirements management plan, stakeholder management plan, project charter, and stakeholder register. These inputs provide a structured approach for collecting, documenting, and managing requirements throughout the project lifecycle. Expert judgment and decision making (option C), feedback from stakeholders and performance data (option B), as well as the scope baseline and project schedule (option A) are not inputs specifically associated with the collect requirements process.