The manage project team process includes managing what type of changes?

  1. Scope changes

  2. Schedule changes

  3. Team changes

  4. Supplier contract changes

The correct answer is: Team changes

The manage project team process in project management involves managing team changes. This process focuses on team members' performance, providing feedback, resolving issues, and coordinating changes to enhance project performance. The other options mentioned - scope changes, schedule changes, and supplier contract changes - are typically managed through other processes like Control Scope, Control Schedule, and Control Procurement.