CAPM Practice Exam 2025 – All-in-One Guide to Master Your Certified Associate in Project Management Exam!

Question: 1 / 885

What is the formula for ETC when prior variances are considered typical?

ETC = BAC + EV

ETC = (BAC - EV)/CPI

ETC = (BAC - EV)/CPI

Explanation

ETC (Estimate to Complete) is a metric used in project management to estimate how much additional budget will be required to complete a project. The formula for ETC when prior variances are considered typical is (BAC - EV)/CPI.

Option A, ETC = BAC + EV, is incorrect because it ignores the impact of prior variances, which can affect the actual cost of the project.

Option C, ETC = AC + BAC, is incorrect because it does not account for the Earned Value (EV) of the project, which is an important component in calculating ETC.

Option D, ETC = (AC - EV)/CPI, is incorrect because it uses the actual cost (AC) instead of the budget at completion (BAC), which is the planned budget for the entire project.

The correct formula, ETC = (BAC - EV)/CPI, takes into account both the budget at completion (BAC) and the earned value (EV), and uses Cost Performance Index (CPI) to adjust for any prior variances. This gives a more accurate estimate of the additional budget needed to

Get further explanation with Examzify DeepDiveBeta

ETC = AC + BAC

ETC = (AC - EV)/CPI

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy