CAPM Practice Exam 2026 – All-in-One Guide to Master Your Certified Associate in Project Management Exam!

Question: 1 / 885

What does 'predecessor' mean in project scheduling?

The initial phase of the project

A task that provides resources for the project

The final activity of the project

The activity that must happen first when defining dependencies between activities in a network

In project scheduling, a 'predecessor' refers to the activity that must happen first when defining dependencies between activities in a network. This means that the predecessor task must be completed before the successor task can begin. It helps in determining the logical sequence of activities in a project to ensure its successful completion. This is why option D is the correct answer.

Options A, B, and C do not accurately define what a 'predecessor' means in project scheduling. The initial phase of the project (Option A) does not specifically relate to the relationship between activities, a task that provides resources for the project (Option B) is not what 'predecessor' signifies, and the final activity of the project (Option C) is referred to as a 'successor' rather than a 'predecessor' in project scheduling terminology.

Get further explanation with Examzify DeepDiveBeta
Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy