Which statement best describes the critical chain method?

  1. It eliminates the need for a project schedule

  2. It adds resource dependencies to the critical path

  3. It is focused solely on budget constraints

  4. It decreases the project's duration significantly

The correct answer is: It adds resource dependencies to the critical path

The critical chain method adds resource dependencies to the critical path, which helps in identifying and managing resource constraints effectively. By incorporating resource dependencies into the critical path, the critical chain method ensures that resources are managed efficiently and that the project schedule is realistic and achievable. This method aims to minimize resource bottlenecks and optimize resource utilization, ultimately leading to better project outcomes. In comparison, the other options are not accurate descriptions of the critical chain method.