CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM exam with our comprehensive quiz that includes engaging questions, detailed explanations, and ample practice resources to help you succeed.

Practice this question and more.


Which one of these is NOT listed as a type of work performance data?

  1. Actual costs

  2. Number of meeting hours

  3. Start and finish dates

  4. Number of defects

The correct answer is: Number of meeting hours

Work performance data includes information such as actual costs, start and finish dates, and number of defects. These data points help the project team assess performance and progress. However, the number of meeting hours is not typically classified as work performance data in project management. While meetings are essential for communication and coordination, the number of meeting hours is considered more of a project management metric rather than work performance data.