Which of these is a source to identify communication requirements?

  1. Stakeholder register

  2. Budget reports

  3. Risk assessments

  4. Quality metrics

The correct answer is: Stakeholder register

The correct answer is A. Stakeholder register. The stakeholder register is a key source for identifying communication requirements in a project. It contains important information about the stakeholders involved in the project, their communication preferences, interests, and influence level. By understanding these details from the stakeholder register, project managers can tailor communication plans to ensure effective and efficient communication throughout the project lifecycle. Options B, C, and D (Budget reports, Risk assessments, and Quality metrics) are not sources specifically focused on identifying communication requirements. While they may provide valuable information in other project management aspects, they do not directly address communication needs and preferences of stakeholders.