Which of the following is NOT an input of plan procurement management?

  1. Project management plan

  2. Stakeholder register

  3. Market research

  4. Risk register

The correct answer is: Market research

In the context of plan procurement management, the inputs generally include the project management plan, stakeholder register, and risk register. Market research, on the other hand, is not typically considered an input to plan procurement management. Market research often falls under the procurement process where potential suppliers are identified, evaluated, and selected. However, market research itself is not a direct input to the planning of procurement management activities within a project.