Which of the following is an output of Plan Risk Management?

  1. Risk Management Plan

  2. Risk Register

  3. Stakeholder Register

  4. Project Management Plan

The correct answer is: Risk Management Plan

The correct answer is A. Risk Management Plan. The Risk Management Plan is an output of the Plan Risk Management process. This plan defines how risk management will be structured and performed on the project. It outlines the approach, methodology, roles and responsibilities, budgeting, timing, risk categories, definitions, and other details related to how risks will be identified, analyzed, and managed throughout the project. Options B, C, and D are incorrect because they are not direct outputs of the Plan Risk Management process. The Risk Register (option B) is an output of the Identify Risks process, the Stakeholder Register (option C) is an output of the Identify Stakeholders process, and the Project Management Plan (option D) is an input to the Plan Risk Management process.