Which of the following is NOT an output of manage stakeholder engagement?

  1. Issue log

  2. Project charter

  3. Change requests

  4. Project documents updates

The correct answer is: Project charter

The project charter is not an output of manage stakeholder engagement. The project charter is an input into the process of managing stakeholder engagement, as it outlines the overall goals, objectives, and stakeholders involved in the project. The outputs of manage stakeholder engagement include the issue log, change requests, and updates to project documents. The issue log tracks any issues or concerns raised by stakeholders, while change requests are submitted for any desired changes to the project that may have been brought up by stakeholders. Finally, project documents may need to be updated to reflect any new information or changes in stakeholder expectations. Therefore, the other three options are all potential outputs of manage stakeholder engagement, while the project charter is not.