Which of the following is NOT an input of the control scope process?

  1. Project management plan

  2. Cost management plan

  3. Requirements documentation

  4. Requirements traceability matrix

The correct answer is: Cost management plan

The control scope process involves monitoring the status of the project scope and managing changes to the scope baseline. Inputs to this process typically include the project management plan, requirements documentation, and the requirements traceability matrix. The cost management plan is not directly related to controlling the project scope; instead, it is more closely associated with managing project costs and budget. Therefore, it is not considered an input to the control scope process.