CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM exam with our comprehensive quiz that includes engaging questions, detailed explanations, and ample practice resources to help you succeed.

Practice this question and more.


Which activity is not considered a part of managing project team change requests?

  1. Moving people to different assignments

  2. Decoding messages effectively

  3. Outsourcing some work

  4. Replacing team members who leave

The correct answer is: Decoding messages effectively

Managing project team change requests involves making changes to the project team in response to identified needs and changes in project requirements. Moving people to different assignments (A), outsourcing some work (C), and replacing team members who leave (D) are all activities that are a part of managing project team change requests. Decoding messages effectively (B) is not directly related to managing project team change requests. While effective communication is important in managing any aspect of a project, decoding messages is not a specific activity associated with managing team change requests.