When does 'close project or phase' occur?

  1. Only at the end of the project

  2. At the start of each phase

  3. At the end of each phase and the project

  4. After each project milestone

The correct answer is: At the end of each phase and the project

Closing a project or phase occurs at the end of each phase and the project as a whole. Option A is not entirely accurate because a project can have multiple phases, and closing a specific phase occurs at the end of that specific phase. Option B is incorrect because closing a project or phase does not happen at the start, but rather at the end. Option D is incorrect because project milestones may occur at various points throughout a project, but closing a project or phase only occurs at the end of each phase and the project.