What reflects the work to be performed and is defined by the WBS over time?

  1. Budget analysis

  2. Schedule

  3. Risk assessment

  4. Quality metrics

The correct answer is: Schedule

A Budget analysis is not the correct answer because it does not reflect the work to be performed over time. It simply looks at the financial aspects of the project and does not take into account the specific tasks and activities that need to be completed. C: Risk assessment is not the correct answer because it focuses on identifying potential risks and creating strategies to mitigate them. While this is an important aspect of project management, it does not reflect the specific work that needs to be done and does not consider the time frame in which it needs to be completed. D: Quality metrics is not the correct answer because it measures the quality of the work that has been completed, rather than reflecting the work to be performed over time. It is an important aspect of project management, but it does not define the specific tasks and activities that need to be completed.