What is the first component of the project management plan?

  1. The project scope statement

  2. The project schedule

  3. The project budget

  4. The project risk plan

The correct answer is: The project scope statement

The first component of the project management plan is the project scope statement. This is because before any project is planned, the scope of the project needs to be identified and defined. The project scope statement outlines the objectives, deliverables, and overall goals of the project. This is the foundation upon which all other components of the project management plan are built. The other options may be important components of the project management plan, but they come after the project scope statement and are not the first component that should be addressed.