What is Project Communications Management concerned with?

  1. Ensuring the project team communicates effectively among themselves

  2. The processes required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and the ultimate disposal of project information

  3. Monitoring external communications and public relations

  4. Developing marketing strategies for project outcomes

The correct answer is: The processes required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and the ultimate disposal of project information

Project Communications Management is concerned with the processes required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and the ultimate disposal of project information. This includes all aspects of communication within a project, involving stakeholders, team members, and other relevant parties. This process helps in efficient communication flow to support successful project outcomes.