CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM exam with our comprehensive quiz that includes engaging questions, detailed explanations, and ample practice resources to help you succeed.

Practice this question and more.


What is contingency reserve?

  1. A fund allocated for project changes and amendments

  2. A budget within cost baseline or performance measurement baseline for accepted risks and developed responses

  3. An additional budget for unforeseen risks and activities outside the project scope

  4. Funds set aside for emergencies and unexpected costs

The correct answer is: A budget within cost baseline or performance measurement baseline for accepted risks and developed responses

Contingency reserve is a budget within the cost baseline or performance measurement baseline that is specifically allocated for known risks and developed responses. It is intended to cover the cost impact of identified risks that have been accepted in the project management plan. This reserve is not for project changes or amendments (Option A), activities outside the project scope (Option C), or general emergencies and unexpected costs (Option D). The correct answer, Option B, best describes the purpose and usage of contingency reserve in project management.