CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM exam with our comprehensive quiz that includes engaging questions, detailed explanations, and ample practice resources to help you succeed.

Practice this question and more.


What is a work package?

  1. A document outlining the project's scope

  2. A tool used for project scheduling

  3. The highest level of a WBS

  4. The lowest level of a WBS; cost estimates are made at this level

The correct answer is: The lowest level of a WBS; cost estimates are made at this level

A work package is the lowest level of a Work Breakdown Structure (WBS). It is a task or deliverable that can be easily assigned to a specific team member or group. Detailed cost estimates are made at this level, which helps in accurately planning and tracking project costs. Work packages are essential for monitoring progress, assigning responsibility, and ensuring that project objectives are met within the allocated budget and timeframe. Options A, B, and C are incorrect because a work package is not a document outlining the project's scope, a tool used for project scheduling, or the highest level of a WBS. These elements are not as detailed as a work package and do not involve the same level of granularity or cost estimation that occurs at the work package level.