What is a milestone list?

  1. A detailed project schedule

  2. A list of project tasks and their durations

  3. A list of significant project points and their dates

  4. A document listing all project risks

The correct answer is: A list of significant project points and their dates

A milestone list is a document that includes significant project points and their corresponding dates. These points indicate critical events or achievements within the project timeline. Milestones help in tracking progress, providing a clear roadmap, and enabling project stakeholders to understand important project stages. Option A is incorrect because a detailed project schedule includes specific tasks, their sequence, resources, and durations, not just significant points. Option B is incorrect because a list of project tasks and their durations focuses on the breakdown of work to be done, not specifically on significant project points. Option D is incorrect because a document listing all project risks highlights potential threats to the project's objectives and is not related to marking significant project points.