CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM exam with our comprehensive quiz that includes engaging questions, detailed explanations, and ample practice resources to help you succeed.

Practice this question and more.


What does weighted three-point estimates or beta/PERT primarily use?

  1. Total project cost

  2. (O + 4ML + P)/6

  3. Standard deviation of project

  4. (P - O)/6

The correct answer is: (O + 4ML + P)/6

Weighted three-point estimates, also known as beta/PERT, primarily use the formula (O + 4ML + P)/6. This formula calculates the expected value of an activity duration by taking a weighted average of three estimates: the optimistic (O), most likely (ML), and pessimistic (P) estimates. By giving more weight to the most likely estimate (4 times the ML estimate compared to 1 time each for O and P), the beta/PERT technique can provide a more accurate and reliable estimation of the activity duration, enabling better project planning and scheduling. Therefore, option B is the correct choice for this question.