What does the stakeholder engagement assessment matrix define?

  1. The budget for stakeholder communication

  2. The roles and responsibilities of project team members

  3. The current state and desired state of stakeholder engagements

  4. The success criteria for project deliverables

The correct answer is: The current state and desired state of stakeholder engagements

The stakeholder engagement assessment matrix defines the current state and desired state of stakeholder engagements. It serves as a tool to assess and measure the level and effectiveness of engagement with stakeholders. This includes analyzing the methods of engagement, communication channels, and level of involvement of stakeholders. Option A is incorrect because the stakeholder engagement assessment matrix is not directly related to budgeting. Option B is incorrect because the roles and responsibilities of project team members are outlined in a separate document, such as a project charter. Option D is incorrect because success criteria for project deliverables are typically outlined in a project management plan, not in the stakeholder engagement assessment matrix.