What does Project Quality Management primarily strive to prevent?

  1. Scope Creep

  2. Budget Overruns

  3. Rework

  4. Resource Overallocation

The correct answer is: Rework

Project Quality Management primarily strives to prevent rework. Rework is a crucial factor that can significantly impact project timelines, budgets, and overall quality. By focusing on preventing rework, project managers can ensure that the project is delivered efficiently, within the defined scope, and meets the required quality standards. Rework not only consumes additional resources but also diminishes stakeholder confidence and can lead to delays in project completion. This is why preventing rework is a key focus area in Project Quality Management.