CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM exam with our comprehensive quiz that includes engaging questions, detailed explanations, and ample practice resources to help you succeed.

Practice this question and more.


What does 'predecessor' mean in project scheduling?

  1. The initial phase of the project

  2. A task that provides resources for the project

  3. The final activity of the project

  4. The activity that must happen first when defining dependencies between activities in a network

The correct answer is: The activity that must happen first when defining dependencies between activities in a network

In project scheduling, a 'predecessor' refers to the activity that must happen first when defining dependencies between activities in a network. This means that the predecessor task must be completed before the successor task can begin. It helps in determining the logical sequence of activities in a project to ensure its successful completion. This is why option D is the correct answer. Options A, B, and C do not accurately define what a 'predecessor' means in project scheduling. The initial phase of the project (Option A) does not specifically relate to the relationship between activities, a task that provides resources for the project (Option B) is not what 'predecessor' signifies, and the final activity of the project (Option C) is referred to as a 'successor' rather than a 'predecessor' in project scheduling terminology.