What are the outputs of perform integrated change control?

  1. Project scope statement and resource calendars

  2. Approved changes and a change log

  3. Risk management plan and activity duration estimates

  4. Stakeholder register and communication plan

The correct answer is: Approved changes and a change log

Perform integrated change control is the process of reviewing all project change requests and managing changes to project deliverables, organizational process assets, project documents, and the project management plan. So, the outputs of this process would be approved changes and a change log. Option A is incorrect because project scope statement and resource calendars are inputs into this process, not outputs. Option C is incorrect because risk management plan and activity duration estimates are not directly related to change control. Option D is incorrect because stakeholder register and communication plan are also inputs, not outputs of this process.