What are the inputs of control stakeholder engagement?

  1. Project management plan, issue log, work performance data, project docs

  2. Change requests, project reports, project presentations

  3. Org process assets, management skills

  4. Meetings, expert judgment, information management systems

The correct answer is: Project management plan, issue log, work performance data, project docs

Inputs of control stakeholder engagement include the project management plan, issue log, and work performance data because these are essential for monitoring the engagement of stakeholders throughout the project. Option B is incorrect because change requests and project reports are inputs for other processes, while project presentations are an output of the control stakeholder engagement process. Option C is incorrect because organizational process assets and management skills are resources used for stakeholder engagement, not inputs. Option D is incorrect because while meetings, expert judgment, and information management systems are tools and techniques for control stakeholder engagement, they are not inputs for the process.