CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM exam with our comprehensive quiz that includes engaging questions, detailed explanations, and ample practice resources to help you succeed.

Practice this question and more.


What are outputs of the manage communications process?

  1. Project communications, Project management plan updates, Project documents updates, Org process assets updates

  2. Communication technology, Communication models

  3. Org culture/structure, Govt/industry standards, PMIS

  4. Sender-receiver models, Choice of media

The correct answer is: Project communications, Project management plan updates, Project documents updates, Org process assets updates

The correct answer is A. Outputs of the manage communications process include project communications, project management plan updates, project documents updates, and organizational process assets updates. Option B (Communication technology, Communication models), Option C (Org culture/structure, Govt/industry standards, PMIS), and Option D (Sender-receiver models, Choice of media) do not accurately represent the outputs of the manage communications process. These options either mention tools and models related to communication or general factors influencing communication, but they do not specifically address the outputs listed in option A.