What are inputs to control procurements?

  1. Weather reports and travel schedules

  2. Project management plan, procurement documents, agreements, approved change requests, work reports, and data

  3. Stakeholder preferences and tastes

  4. Global economic reports

The correct answer is: Project management plan, procurement documents, agreements, approved change requests, work reports, and data

Inputs to control procurements include the project management plan, procurement documents, agreements, approved change requests, work reports, and data. These inputs are essential for effectively managing and controlling the procurement process throughout the project lifecycle. Weather reports and travel schedules, stakeholder preferences and tastes, and global economic reports are not direct inputs to control procurements and are not typically used for this purpose in project management.