What are inputs of perform quantitative risk analysis?

  1. Risk management plan, cost management plan, schedule management plan, risk register, enterprise environmental factors, organizational process assets

  2. Project charter, stakeholder register

  3. Quality management plan, resource management plan

  4. Communications management plan, stakeholder engagement plan

The correct answer is: Risk management plan, cost management plan, schedule management plan, risk register, enterprise environmental factors, organizational process assets

The correct answer is A. Inputs of perform quantitative risk analysis include the risk management plan, cost management plan, schedule management plan, risk register, enterprise environmental factors, and organizational process assets. Options B, C, and D do not include the key inputs required for perform quantitative risk analysis. These inputs are essential for assessing and analyzing risks in a project to quantify their potential impacts on project objectives.