What are included in risk diagramming techniques?

  1. Risk register and SWOT analysis

  2. Cause and effect diagrams, system or process flow charts, influence diagrams

  3. Risk management plan and enterprise env factors

  4. Risk probability and impact assessment

The correct answer is: Cause and effect diagrams, system or process flow charts, influence diagrams

Risk diagramming techniques are used to identify risks and create visual representations of how they are interconnected. These techniques generally involve creating diagrams or maps to show the relationship between risks and potential causes or effects. Option A, risk register and SWOT analysis, may be part of risk management but are not diagramming techniques. Option C, risk management plan and enterprise environmental factors, refer to documents and factors that may be used as inputs or outputs of risk diagramming techniques but are not techniques themselves. Option D, risk probability and impact assessment, is a specific type of risk analysis but is not a diagramming technique.