How are cost estimates for each work package processed in cost aggregation?

  1. Evaluated for risks

  2. Adjusted for inflation

  3. Added together for the entire project

  4. Reviewed for accuracy

The correct answer is: Added together for the entire project

Cost estimates for each work package are processed in cost aggregation by adding them together for the entire project. This aggregation of the cost estimates from the different work packages gives a comprehensive view of the total project cost. This final total cost estimate is crucial for project planning, budgeting, and overall cost management. The other options are not the correct answers because they do not accurately describe the process of cost aggregation in this context.