CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM exam with our comprehensive quiz that includes engaging questions, detailed explanations, and ample practice resources to help you succeed.

Practice this question and more.


During risk reassessment, what should be reviewed?

  1. The budget and resources

  2. Key risks, changes, any new risks

  3. Technical accomplishments

  4. The amount of contingency reserves

The correct answer is: Key risks, changes, any new risks

During risk reassessment, key risks should be reviewed to determine if there are any changes or new risks that have emerged. Options A and D may be relevant in the overall risk management process, but they are not specifically related to risk reassessment. Option C is not directly related to risk at all.